Scape Todman is our eighth major student accommodation construction project to be delivered by Infinity Constructions for client Scape Australia. Located on the corner of Anzac Parade and Todman Avenue in Kensington, the development provides high-quality, modern student living designed to support wellbeing, safety, and community connection.

The project demonstrates Infinity’s expertise in large-scale multi-residential construction, complex staging, and the delivery of high-quality finishes within a dense operational urban environment.

Project Highlights:

Positioned near the UNSW university precinct, the development comprises an 18-storey building with a single basement level. The ground floor and Level 1 include retail tenancies, a central lobby, and building management facilities servicing the wider development.

Level 2 features extensive communal and multi-purpose spaces designed to foster student interaction and collaboration. Levels 3 to 16 accommodate student residences, complemented by integrated landscaped areas throughout the building. Level 17 includes a communal library and dedicated study spaces for residents.

The development has been designed to deliver secure, functional, and community-focused accommodation that supports the modern student lifestyle. Construction methodologies prioritise build quality, acoustic performance, fire safety, and long-term durability in accordance with PBSA requirements and Australian building standards.

Key Construction Features

  • 18-storey reinforced concrete structure with one basement level
  • Retail tenancies across the ground floor and Level 1
  • Dedicated lobby and building management facilities
  • Large multi-purpose communal student spaces on Level 2
  • Student accommodation across Levels 3 to 16
  • Communal library and study areas on Level 17
  • Integrated building services and plant areas
  • High-performance façade and building envelope systems
  • Compliance with PBSA and Australian building standards

Project Status

  • Project is forecast for completion Mid 2027

Infinity Constructions Capability

This project reflects Infinity Constructions’ proven capability to deliver complex vertical accommodation projects in live urban environments. The team manages stakeholder coordination, safety compliance, and programme delivery while maintaining quality and cost control. Repeat appointments from Scape Australia demonstrate trust in Infinity’s project management systems and construction expertise. Infinity Constructions is proud to be the trusted Sydney construction company bringing this important project to life.

SCAPE TODMAN 5th MAY 2026 (23)

Construction Progress Update

Construction is continuing to progress at Scape Todman in Kensington, with the jumpform advancing ahead of the floor and ceiling slabs as the reinforced concrete structure rises. The aerial sequence below shows the pace of construction between May and July 2026, while recent site views highlight ongoing slab pours and the retention of the heritage façade along the street frontage.

Aerial view of Scape Todman construction in Kensington in May 2026

May 26

Aerial view of Scape Todman construction in Kensington in June 2026

June 26

Aerial view of Scape Todman construction in Kensington in July 2026

July 26

scape todman jumpform slab pours kensington

The jumpform progresses several floors ahead of the active floor and ceiling slab construction as the building rises.

scape todman heritage facade construction kensington

Street-level view showing the retained heritage façade while construction and the jumpform continue above.